On Thursday 29 November 2001 12:35 pm, you wrote:
> In general, I think that we should freeze and run all regression tests at
> least three or four days (perhaps even a week) before release so we have
> time to react. (bind had a failure on SGI MIPSpro as well.)
I agree. I would think that 3-4 days before release we should branch CVS and
tag it appropriately (e.g., boost_1_26_0) and release only from branches.
That way we can stabilize code on the branch without playing the waiting game
on newer (but not stable) changes.