Boost logo

Boost :

From: Douglas Gregor (gregod_at_[hidden])
Date: 2001-11-29 15:17:27


On Thursday 29 November 2001 12:35 pm, you wrote:
> In general, I think that we should freeze and run all regression tests at
> least three or four days (perhaps even a week) before release so we have
> time to react. (bind had a failure on SGI MIPSpro as well.)

I agree. I would think that 3-4 days before release we should branch CVS and
tag it appropriately (e.g., boost_1_26_0) and release only from branches.
That way we can stabilize code on the branch without playing the waiting game
on newer (but not stable) changes.

        Doug


Boost list run by bdawes at acm.org, gregod at cs.rpi.edu, cpdaniel at pacbell.net, john at johnmaddock.co.uk