Doug Gregor wrote:

[...]

> Ouch, sorry. I didn't realize it was normal for the Tru64 tests to
> run for 7 days.
>
> In that case, we cannot consider Tru64 a release-critical platform,
> and it should be removed from the release view of the regression
> tests. Any platform with 7-day cycle times will lengthen a release
> schedule. Of course, regression testing for the platform is still
> important, and we'll still try to get everything we can working for
> that compiler.

I removed the older compiler version from the regression test runs, which
hopefully will cut the needed time down to 48 hours for a full run, would
that be sufficient to be qualified as release platform?

Markus