Subject: Re: [boost] Major code changes deadline approaching
From: Belcourt, Kenneth (kbelco_at_[hidden])
Date: 2009-12-30 12:32:24


On Dec 27, 2009, at 5:03 PM, Belcourt, Kenneth wrote:

>
> On Dec 27, 2009, at 1:29 PM, Marshall Clow wrote:
>
>> On Dec 27, 2009, at 11:21 AM, Vladimir Prus wrote:
>>> Boosters,
>>>
>>> The deadline for "major code changes" for 1.42 is Monday, January
>>> 4, 2010. Please
>>> try to get all big features merged to release branch by that date,
>>> and let the
>>> release team know if there are any issues.
>>>
>>> The next deadline will be Jan 11, when the release branch will be
>>> closed for all
>>> changes, except by explicit permission.
>>>
>>> -- The Release Managers,
>>>
>>> Beman Dawes
>>> Daniel James
>>> Eric Niebler
>>> Rene Rivera
>>> Vladimir Prus
>>
>> I'd just like to point out that we have
>> 28 open tickets marked as "Showstoppers": https://svn.boost.org/trac/boost/report/29
>> and 14 open tickets marked as "Regressions": https://svn.boost.org/trac/boost/report/30
>
> And I'd also like to draw your attention to an outage beginning Dec 29
> of unspecified duration (to replace a network switch and other
> upgrades). This outage will impact both release and trunk reporting
> as well as all Sandia testers. Optimistically we should be
> operational within a day but, given the holidays and other factors, it
> could be as late as Jan 4th before things come back online.

Our switch was replaced and things seem to be working okay. I've
restarted both the reporting and the Sandia testers.

-- Noel


Boost list run by bdawes at acm.org, gregod at cs.rpi.edu, cpdaniel at pacbell.net, john at johnmaddock.co.uk