Boost logo

Boost Testing :

From: Aleksey Gurtovoy (agurtovoy_at_[hidden])
Date: 2007-08-01 14:34:32


Boris Gubenko writes:
> Latest results for RC_1_34_0 are dated: Mon, 30 Jul 2007 10:21:37
> +0000. So, it looks like the report generation is stalled. Is it
> intentional?

I had to suspend RC_1_34_0 pages updates in favor of what will become
the final 1.34.1 results:

http://engineering.meta-comm.com/boost-regression/boost_1_34_1/developer/summary.html

>
> Latest results for Version_1_34_1 (so called "final test run") are dated:
> Wed, 1 Aug 2007 01:38:55 +0000. However, there are only two platforms
> there: HP-UX and SunOS.
>
> I'm not sure what's expected:
>
> . should testing with "--tag RC_1_34_0" continue?
>
> . should testing with "--tag Version_1_34_1" continue?

Just one test run with "--tag Version_1_34_1" is sufficient.

-- 
Aleksey Gurtovoy
MetaCommunications Engineering

Boost-testing list run by mbergal at meta-comm.com